Signed: Heidi Wilson, Clerk & RFO Dated: 27 August 2025
 
AGENDA
 
The parish council committee may pass a resolution on any agenda item, even if the agenda does not specifically state ‘to resolve to approve’.  This wording ‘to resolve to approve’ in certain circumstances could be interpreted as predetermination.  The parish council have received advice from LALC in relation to this matter.
The Staffing Committee operates within the limits of the agreed Terms of Reference and as such may need to make recommendations to full council for a resolution. 
 
1. Chair’s Welcome (Safety Announcements)
 
2. Public Forum: Fifteen minutes will be set aside for Members of the Public to ask questions or make short statements to the Council.  The Council may choose not to answer any question; a response may instead be given in writing.  Matters raised may be added to an agenda for a future meeting.  Members of the public are welcome to stay for the Parish Council meeting after the public session but are not permitted to speak during the meeting.  If you would like to make comment during the meeting, please raise your hand if you are able to do so. 
 
3. Councillors present
 
4. Apologies
Apologies for absence and reasons given.
 
5. To receive any reports of member’s interest, pecuniary or otherwise in relation to the agenda and any dispensations in accordance with the Localism Act 2011
 
6. Minutes
a) To resolve to accept the minutes of the meetings held on 6 March, 14 April and 2 June as a true and accurate record of those meetings. 
 
7. Health & Safety
a) To note that the Fire Risk Assessment has been scheduled for 15 October 2025.  
b) To note that Urisk will be on site on 13 October 2025 in relation to legionella testing and remedial work.
 
8. General Items
a) To note the EPC rating awarded to the Pavilion. 
b) To receive an update from Councillor Spencer further to a meeting with Smith’s Civil and Engineering in relation to their proposals for a MUGA.  
c) To discuss placement of the cricket storage unit further to complaints received from a neighbouring resident. 
d) To receive an update from Councillor Spencer in relation alterations to the fencing and storage at the Pavilion (at the request of the tenant, Mr Warrilow).
 
9. Finance
a)
i) To receive a summary of all improvement works to the building to date and associated costs in the 2024/25 financial year (does not include inspections or testing).
 

SKU Electrical

3 Phase Supply to the kitchen area & Loft space inspection and testing of all circuits including extending and routing cabling, relocating junction boxes and rewiring as necessary.  Replace extractor fan in accessible toilet (deposit).

1666.67

333.33

2000.00

Richard Wells

Replacement lead flashing/roof tiles

2182.00

0.00

2182.00

SKU Electrical

Electrical works at the Pavilion

6034.17

1606.83

7641.00

Richard Wells Plastering

Roof Tunnels to single storey roof including felt and batten.

600.00

0.00

600.00

 

SKU Electrical

Completion of electrical work including installation of fishtail switches, emergency lighting, rewiring of accessible toilet, new kitchen sockets and EICR.

2716.67

543.33

3260.00

 

Kyme Heating

Rectify dead legs, supply and fit copper pipework, relocate radiator

2500.00

0.00

2500.00

Richard Wells Plastering

Conversion of garage to store

2400.00

0.00

2400.00

 

Richard Wells Plastering

Loft insulation plus 3 days

3153.84

0.00

3153.84

 

Sleaford Windows

Boarding/Glazing

709.00

141.80

850.80

SKU Electrical

Armoured Cable Repairs

485.00

97.00

582.00

SKU Electrical

Pavilion Changing Room Electrical Conversion

1816.67

363.33

2180.00

Richard Wells Plastering

Changing Room Conversion/Voids Pavilion

5190.00

0.00

5190.00

Clearly Better Windows

Replacement windows

3961.18

787.83

4749.01

 

 

33,415.20

3,873.45

37,288.65

ii) To review the (outstanding) priorities list for 2025/26 further to an informal meeting of the Pavilion Committee (taken from the informal meeting of the Pavilion Committee on Sunday 8 June 2025 – completed works have been removed).
 

FRA Compartmentation, means of escape, cavities and voids.

  • Exterior side gate (locking mechanism).
  • Replacement fire doors (function room WC, bar to function room as the roller shutter door is not fire resistant; this will include creating a new access, function room to bar (double doors), boiler room, bar to corridor, corridor, loft)
  • Repair voids left by the electrician and to clad the loft hatch in the corridor with fire lined plasterboard.
  • The fire wall in the loft need remedial action.
  • Corridor storage/changing room wall does not meet required standard for compartmentation.
  • Fire alarms and smoke detection in the loft, store and cellar.
  • The ground surface presents a hazard along the escape route.  As a temporary measure the gravel grids from the old playground could be used to level out the ground at the base of the fire escape.
  • Fire extinguisher signage.

H&S flooring

Clerk to obtain a quote for the floor to be levelled off and resurfaced (from the function room through to the bar and within the accessible toilet)

Drains and guttering

Temporary repairs to seal in 2025/26  Replacement for future scheduling in 2026/27.

Legionella

Mandatory works scheduled for October 2025.  Outstanding remedial work will be scheduled for 2026/27

Replace lighting pole

Moss removal

 
b) To review the budget for 2026/27 with a view conducting further research and making recommendations to the Parish Council with consideration of outstanding building work. 
i) Budget heads and identified works for consideration:
• Maintenance (Buildings)
• Maintenance (Outside/including tree maintenance)
• Inspections/Testing (Legionella, boiler servicing, fire alarm, fire extinguisher, emergency light, FRA, Asbestos risk assessment, PAT)
• (Special) Projects (MUGA)
• Reserves (new roof/renovation)
 

Works for 2026/27 and beyond

Estimated Cost

Drain repairs (survey 18 needs to be re-surveyed which may lead to additional expenditure).  The estimate is based on lorry and CCTV for one day only. 

£8000.00 plus VAT

Guttering and drainpipes

£2,100.00 inc VAT

External works and redesigned perimeter fencing to ensure unobstructed means of escape.

£13,125.00 inc VAT

External emergency lighting (see FRA, October 2025)

Specification not available.  Quote not requested.

Accessible changing room (pending survey from Access Able)

Specification not available.  Quote not requested.

New pathway

Specification not available.  Quote not requested.

H&S Flooring

Estimates pending

Legionella remedial work

4,900.00 inc VAT

Redecoration

2027/28

 
9. Date and time of the next meeting
10. Questions from the public (time permitting at the discretion of the Chair).
If you require a more detailed version of the agenda, please contact the Clerk.
If you would like to attend the Parish Council meeting and have accessibility requirements, please contact the Clerk ahead of time so that reasonable adjustments can be made.